CompTIA PK0-004 Dumps

CompTIA PK0-004 Dumps PDF

CompTIA Project +
  • 796 Questions & Answers
  • Update Date : December 01, 2024

PDF + Testing Engine
$65
Testing Engine (only)
$55
PDF (only)
$45
Free Sample Questions

Why is ITExamsLab the best choice for certification exam preparation?

ITExamsLab is dedicated to providing CompTIA PK0-004 practice test questions with answers, free of charge, unlike other web-based interfaces. To see the whole review material you really want to pursue a free record on itexamslab A great deal of clients all around the world are getting high grades by utilizing our PK0-004 dumps. You can get 100 percent passing and unconditional promise on PK0-004 test. PDF files are accessible immediately after purchase.

A Central Tool to Help You Prepare for CompTIA PK0-004 Exam

itexamslab.com is the last educational cost reason for taking the CompTIA PK0-004 test. We meticulously adhere to the exact audit test questions and answers, which are regularly updated and verified by experts. Our CompTIA PK0-004 exam dumps experts, who come from a variety of well-known administrations, are intelligent and qualified individuals who have looked over a very important section of CompTIA PK0-004 exam question and answer to help you understand the concept and pass the certification exam with good marks. CompTIA PK0-004 braindumps is the most effective way to set up your test in only 1 day.

User Friendly & Easily Accessible on Mobile Devices

Easy to Use and Accessible from Mobile Devices.There is a platform for the CompTIA PK0-004 exam that is very easy to use. The fundamental point of our foundation is to give most recent, exact, refreshed and truly supportive review material. Students can use this material to study and successfully navigate the implementation and support of CompTIA systems. Students can access authentic test questions and answers, which will be available for download in PDF format immediately after purchase. As long as your mobile device has an internet connection, you can study on this website, which is mobile-friendly for testers.

CompTIA PK0-004 Dumps Are Verified by Industry Experts

Get Access to the Most Recent and Accurate CompTIA PK0-004 Questions and Answers Right Away:
Our exam database is frequently updated throughout the year to include the most recent CompTIA PK0-004 exam questions and answers. Each test page will contain date at the highest point of the page including the refreshed rundown of test questions and replies. You will pass the test on your first attempt due to the authenticity of the current exam questions.

Dumps for the CompTIA's PK0-004 exam have been checked by industry professionals who are dedicated for providing the right CompTIA PK0-004 test questions and answers with brief descriptions. Each Questions & Answers is checked through CompTIA experts. Highly qualified individuals with extensive professional experience in the vendor examination.

Itexamslab.com delivers the best CompTIA PK0-004 exam questions with detailed explanations in contrast with a number of other exam web portals.

Money Back Guarantee

itexamslab.com is committed to give quality CompTIA PK0-004 braindumps that will help you breezing through the test and getting affirmation. In order to provide you with the best method of preparation for the CompTIA PK0-004 exam, we provide the most recent and realistic test questions from current examinations. If you purchase the entire PDF file but failed the vendor exam, you can get your money back or get your exam replaced. Visit our guarantee page for more information on our straightforward money-back guarantee.

Related Exams


CompTIA PK0-004 Sample Questions

Question # 1

Upon assignment to a project, the project manager is given a set budget, a due date, and a clearly defined description of desired deliverables. Which of the following should the project manager do NEXT?

A. Determine the flexibility between the project constraints
B. Hold a kick-off meeting with the project team
C. Determine procurement needs to meet the project demands
D. Create the risk register



Question # 2

Analogous estimating was used earlier in a hauling project; however, through progressive elaboration, it is determined that the cost for fuel is much lower than anticipated. Which of the following types of project change should be submitted?

A. Resources
B. Requirements
C. Scope
D. Funding



Question # 3

A project manager has taken over a project that is already in progress. The project manager notices the functional manager of one team is unaware of the current progress. Which of the following should the project manager do? (Choose two.)

A. Update the project charter to include the functional manager as a key stakeholder
B. Publish the project schedule to the functional manager
C. Review the communications plan to ensure proper involvement
D. Add the incident to the issue log and seek resolution
E. Ensure the functional manager is on the status report distribution list



Question # 4

A hurricane occurs in an area where several key project resources are located. When reviewing the project dashboard, the project sponsor sees the project is behind schedule and asks the project manager for an explanation. Which of the following documents should the project manager examine NEXT to provide an explanation? 

A. Meeting minutes
B. Issue log
C. Project schedule
D. Budget



Question # 5

A project manager is assigned a project that is part of the company’s strategic objectives. Of which of the following is the project a part?

A. Project management office
B. Portfolio
C. Program
D. Mission statement



Question # 6

A project manager is starting a project on an unfamiliar technology. The document that is MOST likely to be created and distributed is an: 

A. RTM
B. RFQ
C. RFI
D. RFP



Question # 7

A project team is working on a project with high public visibility and excitement. The project sponsor is concerned the public may lose interest due to the long delivery timeline. Which of the following is the BEST way to keep the external stakeholders informed and engaged throughout the project?

A. Video conferencing
B. Instant messaging
C. Social media
D. Email



Question # 8

Which of the following represents the order of the team development stages? 

A. Forming, storming, norming, performing
B. Forming, performing, storming, norming
C. Forming, norming, storming, performing
D. Forming, norming, performing, storming



Question # 9

Which of the following should a project manager consider as part of a make or buy analysis? 

A. Organization type
B. KPIs
C. Project charter
D. Trade secrets



Question # 10

A project has been experiencing some difficulties due to third-party vendors. The project manager should request. 

A. Additional resources
B. A gate review
C. A risk register update
D. A performance audit



Question # 11

Which of the following are characteristics of a matrix organization? (Choose three.) 

A. The project manager has full authority.
B. Resources report directly to the functional manager.
C. Authority is shared between functional and project managers.
D. Resources are assigned from functional area to project.
E. There is ad hoc resourcing.
F. The organization utilizes a bench.
G. The project manager authority ranges from strong to weak.



Question # 12

Which of the following organizational structures uses project team members who are selected from within their department?

A. Projectized
B. Balanced matrix
C. Functional
D. Strong matrix



Question # 13

The PMO has asked the PM to provide a status report indicating the number of events and activities required to complete a project. Which of the following charts should the PM include in the status report?

A. Gantt chart
B. Scatter chart
C. Run chart
D. Process diagram



Question # 14

Which of the following is a risk strategy? 

A. Risk quantification
B. Risk avoidance
C. Risk identification
D. Risk review



Question # 15

A project sponsor approved an undocumented change without following the formal change control process. The resulting change caused an outage in a crucial accounting application. Which of the following change control processes would help mitigate the realization of this risk?

A. Regression plan
B. Quality plan
C. Change validation
D. Application version control